Insert Light Fixture Project Schedule
A light fixture schedule that lists all of the light fixtures used in the current project can be inserted on the drawing.
To insert this schedule onto the drawing, go to
Ribbon: DM Photometrics→Schedule→ Insert
Pulldown Menu: DM Photometrics→Light Fixture Schedule→Insert Light Fixture Project Schedule
Insert Light Fixture Project Schedule Dialog Box
-
Schedule Notes: A note that will appear below the schedule when inserted on the drawing.
-
☐ Maximum Schedule Height: Whether the schedule has a maximum height. This height is inches on the printed page.
If this is not checked, the schedule will be in a single schedule.
If this is checked, you can specify the maximum height of the schedule. When the schedule exceeds this height, it will be continued in a second schedule next to the first. The label of the second schedule will have the Schedule title continued label option added to it to indicate that it is a continuation of the first schedule. Visit the Schedules options section for more information.
-
Press this button to specify the ☐ Maximum Schedule Height on the drawing. The dialog box will be closed and you will be prompted to specify the height.
Specify maximum schedule height:
The distance you enter on the drawing will be used as the maximum height. It is simplest to draw a line straight down to where the bottom of the schedule should be located.
-
☐ Zoom to Schedule After Insertion Whether the display will be moved to the schedule location after it has been inserted or updated.
-
☐ Show Unused Light Fixtures Whether light fixtures in the schedule that have not been inserted on a drawing will be displayed in the schedule.
-
Press this button to modify the layout of the light fixture schedule on the drawing. Visit the Edit Light Fixture Schedule Layout section below for more information.
Edit Light Fixture Schedule Layout
The Light Fixture Schedule Label Display and Order dialog box is used to configure the appearance of the light fixture schedule on the drawing for the current project.
To change the appearance in the master database for future projects, use the Edit Light Fixture Schedule Master Settings command.

Grid Columns
-
Key ☰ The identifier for the column, describing what value it will display. The value in this column is fixed and cannot be changed.
-
Label The name that will be displayed for the column.
-
Width The width of the column in inches on the printed drawing.
-
Justification ▾ The justification of the text values in the column. The justification of the title for the schedule and of the column headers are set using the Schedule title justification ▾ options and the Schedule column label justification ▾ option in the Options command.
- Left The text is left-justified.
- Center The text is center-justified.
- Right The text is right-justified.